
|
Airport Way South Phase II - South Royal Brougham Way to South Dearborn Street
Project Update: July 26, 2011
Project Nearly Complete
The 2010 project to pave Airport Way South from South Royal Brougham Way to South Dearborn Street is nearly complete. In late summer 2011 the contractor will return to stripe segments of the roadway.
The project was due to wrap up late last year but inclement weather and unforeseen circumstances impacted the schedule. Updates will be posted here as they are confirmed. |
Project Overview
The Seattle Department of Transportation (SDOT) is continuing its work to improve streets and help keep traffic moving when major construction gets underway on the Alaskan Way Viaduct. On March 22, 2010 SDOT began making a series of improvements to Airport Way South from South Spokane Street to South Dearborn Street. This street serves as a major north/south freight corridor in the SODO/Duwamish area. This project along with other paving projects going on in the area are funded by the “Bridging the Gap” transportation levy approved by Seattle voters in November 2006. Phase I of the Airport Way S is complete. Phase II construction began August 9, 2010. Substantial completion was planned for December 2010 however, inclement weather contributed to shifting some limited remaining work to 2011.
Project Description
Phase II – South Royal Brougham Way to South Dearborn Street
This segment will be completely reconstructed with concrete pavement from S Royal Brougham Way to S Dearborn Street. As part of this work, a bicycle route is being added between S Royal Brougham Way and 6th Avenue South.

Schedule
Phase Two
|
Design Completion |
|
May 2010 |
Bid Advertisement |
|
June 2010 |
Construction Starts |
|
August 2010 |
Substantial Completion |
|
Summer 2011 |
Funding
Both phases of this project are funded by Bridging the Gap, the $365 million levy passed by Seattle voters in November of 2006
Project Contacts
- LeAnne Nelson, Public Information Officer, Seattle department of Transportation, email: leanne.nelson@seattle.gov ; Telephone: (206) 684-3897
- Terrance Plumb, Project Manager, Seattle Department of Transportation Email: Terrance.plumb@seattle.gov ; Telephone: (206) 733-9053
|