Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
Link to Transportation Home Page Link to Transportation Home Page Link to Transportation About Us Page Link to Transportation Contact Us Page
Delivering a first-rate transportation system for Seattle Scott Kubly, Acting Director

Services 

Projects 

Planning 

Resources 

Events

News

Site Index


Street Maintenance Program
Pavement Management
Current Paving Projects
Recent Paving Projects
Bridge Painting Projects
Bridge Rehabilitation, Replacement and Seismic Retrofit
Pothole Rangers
Street Maintenance Request Form

Marion Street – Western Avenue to Sixth Avenue & Columbia Street – First Avenue to Second Avenue

 


This project has reached “physical completion.” Thank you for your patience during the construction.

 

October 7, 2009

Work Happens October 9, 10, 11:
SDOT’s paving contractor will perform grinding and paving work at the intersection of First Avenue & Columbia Street and on Columbia Street up to approximately 100 feet east of the intersection on the weekend of October 9th through October 11th. 

  • Construction crews will grind and remove existing asphalt pavement at the intersection on Friday night starting at 6:30 PM.  Expect noisy conditions.
  • On Saturday and possibly Sunday, construction crews will adjust utility covers and repave the intersection.

 Traffic Impacts:

  • First Avenue will be closed between Marion Street and Cherry Street.
  • Columbia Street will be closed at Second Avenue.
  • The Columbia Street on-ramp to Alaskan Way Viaduct will be closed.
  • Detour route signs will be posted.
  • Sidewalks and crosswalks will be temporarily closed.
  • Uniformed police offices and flaggers will be on site to assist pedestrians and general traffic near the crosswalks

September 18, 2009

Construction Restarting on Marion Street
Mostly Night Work for Next Three Weeks

September 10-11:

  • SDOT’s contractor will do daytime saw-cutting work in preparation for asphalt base repair next week.  There will be some periodic lane closures and parking restrictions on Marion Street between Western and Sixth avenues.

September 14-18:

  • The contractor will restart major work on Marion Street repairing the roadway base to the asphalt section of the
    street and adjusting utilities between Western Avenue and Sixth Avenue.  The base repair will occur during the night shift, 6:00 PM to 6:00 AM, September 14-17. 
  • Traffic will be reduced to one lane 24/7 between Western and First avenues and one lane during non-peak hours between First and Fifth avenues. Marion will be periodically closed between Fifth and Sixth avenues

for base repairs.

  September 18-19:

  • Construction crews will grind and remove the old asphalt surface. The work will be done at night and on a weekend, 7:00 PM Friday evening to 6:00 AM Saturday morning.
  • There will be parking restrictions, and traffic will be reduced to one lane on Marion Street.  There will be brief crossing restrictions at intersections.

September 21-23:

  • Asphalt paving crews will pave Marion Street along the entire stretch of roadway between Western and Sixth avenues. The concrete section of roadway has already been paved. The work will be done at night, 6:00 PM to 6:00 AM each day.
  • There will be parking restrictions, and traffic will be reduced to one lane on Marion Street.  There will be temporary crossing and turning restrictions at intersections.

September 24-30:

  • Construction crews will install temporary and permanent pavement markings, and substantially complete the project.
  • There will be some periodic lane closures and parking restrictions

The above schedule depends on weather conditions.

 

The Seattle Department of Transportation (SDOT) is making improvements to several arterials in Downtown Seattle in 2009. The projects are funded by the “Bridging the Gap” transportation levy approved by Seattle voters in November 2006.

SDOT is planning to make improvements to Marion Street, between Western Avenue and Sixth Avenue, starting in late July or early August 2009. The project is expected to be completed by early October 2009.

Project Description

The project will include new concrete and asphalt pavement, upgraded curb ramps, and some areas of replaced sidewalk. 

Originally scheduled for 2010 construction, this project was accelerated as part of the Mayor's economic stimulus package, called "Seattle Jobs Forward", to create jobs and revive the local economy. The "Seattle Jobs Forward" is a package of immediate local action to create direct jobs and boost Seattle’s economy over the next two years.

What to Expect During Work  

  • Lane closures
  • Pedestrian and vehicle detours
  • Parking and loading restrictions
  • Moderate construction noise and dust
  • Week day & weekend work activity
  • Some night work
  • Regular notices with additional information during construction
  • Access maintained to all businesses and residences

Project Contacts
Susan Byers, Project Manager, susan.byers@seattle.gov, (206) 733-9076
George Frost, Public Outreach Coordinator, george.frost@seattle.gov, (206) 615-0786

Paving Area Map

Home | About Us | Contact Us | Site Index | News | FAQs | E-Mail Alerts