Street Maintenance Program
Pavement Management
Current Paving Projects
Recent Paving Projects
Bridge Painting Projects
Bridge Rehabilitation, Replacement and Seismic Retrofit
Pothole Rangers
Street Maintenance Request Form

Denny, Dexter, and Mercer Repaving Project

The Citys Arterial Asphalt and Concrete Program resurfaces a number of streets each year. Denny Way, Dexter Avenue N, and Mercer Street are scheduled for 2007. This project is funded by the "Bridging the Gap" Transportation Initiative approved by Seattle voters in November 2006.

As of Friday, August 24th, the project reached substantial completion. The only work remaining, if any, would be minor corrections to work already done.


July 27, 2007 Update on the Denny Way/Dexter Avenue N/ Mercer Street Paving Project

Denny Way ( 1st Avenue N to 9th Avenue N )

Construction crews have completed paving Denny Way and are now working on installing traffic detector loops and new curb ramps, as well as upgrading existing curb ramps. The work will be taking place over the next two weeks. Work on individual curb ramps will take two to three days each, and require partial closure of adjacent traffic lanes and curb and sidewalk areas. Pedestrian access will be maintained to businesses and residences.

All lanes of traffic will be open from 6:00 AM to 9:00 AM , and 3:00 PM to 6:00 PM , Monday through Friday. Traffic may be reduced to one lane in each direction at other times.

Mercer Street ( Queen Anne Avenue N to 5th Avenue N )

Pavement striping is scheduled to take place the first week in August and may take approximately two to three days to complete. Traffic may be restricted to specific lanes during the lane markings.

Dexter Avenue N (Denny Way to Mercer Street )

Minor work in spot locations is scheduled for completion the first week in August.

  • Business access will be maintained
  • Bicyclist traffic may have to merge with vehicular traffic. Appropriate signs will be posted.

The Denny/Dexter/Mercer Street Paving project began on April 23, 2007 . Funding is provided by the “Bridging the Gap” transportation funding package approved by voters in November 2006.

 

July 18, 2007 Denny/Dexter Traffic Advisory

(Seattle) - Overnight July 19 construction crews are scheduled to finish paving Denny Way from Dexter Ave. to Westlake Ave. The work is set to begin at 7 p.m. and is expected to be finished by 6 a.m. the next morning, July 20th. The work is weather dependent so rain Thursday night may cause a delay.

Dexter Avenue N, between Republican Street and Mercer Street, will be used as a staging area for construction equipment and materials. Traffic will likely be reduced to one lane in each direction during transfer of construction materials. The northbound bike lane on Dexter will also be affected. Flange and uniformed police officers will be used for traffic control. Staging the material on Dexter will allow the contractor to take up less space on Denny Way.

Current construction on Denny Way includes repair of the roadway base, installation of traffic signal detector loops, and adjustments to utility (manhole) castings. All lanes of traffic on Denny will be open during rush hour, from 6:00 AM to 9:00 AM and 3:00 PM to 6:00 PM, Monday through Friday. Traffic may be reduced to one lane in each direction at other times, including during the nighttime paving work.

The Denny/Dexter/Mercer Street Paving project began on April 23, 2007. Improvements along Dexter are now complete and those on Mercer are wrapping up. The City’s Arterial Asphalt and Concrete Program will resurface a number of streets each year. Funding is provided by the “Bridging the Gap” transportation funding package approved by voters in November 2006.


July 10, 2007 Special Update on Dexter Avenue N

The Denny/Dexter/Mercer Street Paving project began on April 23, 2007 . Funding is provided by the “Bridging the Gap” transportation funding package approved by voters in November 2006. Here is an update on the project’s schedule:

Dexter Avenue N (Denny Way to Mercer Street )

  • Only minor clean-up and restoration remains. This work will be completed by the end of next this week.
  • Dexter Avenue N, between Republican Street and Mercer Street, will be used during the two paving phases on Denny Way (see below) as a staging area for construction equipment and materials. The staging area will occupy one lane on the east side of Dexter. Staging the material on Dexter will allow the contractor to take up less space on Denny Way during the paving operations.
  • On-street parking will be prohibited as needed for staging between Harrison Street and Republican Street.
  • Traffic on Dexter Avenue N will likely be reduced to one lane in each direction during transfer of construction materials. The northbound bike lane on Dexter will also be affected. Flaggers and uniformed police officers will be used for traffic control.

Denny Way ( 1 st Avenue N to 9 th Avenue N )

  • Asphalt paving of the roadway will take place in two phases : .
    • Phase 1- The first phase (Denny Way from 1 st Avenue N to 6 th Avenue N ) is scheduled for night work Friday, July 13 and day work Saturday, July 14. This work is weather dependent will be nighttime, weekend work, and depend on weather conditions .
    • Phase 2 - The second phase (Denny Way from 6 th Avenue N to Westlake/9 th Avenue N) is scheduled to take place at night the week of between July 1 5 6 and - July 19 20 . This will be nighttime, weekday work, and depend on work is weather conditions dependent .
  • Night work hours are The hours for both phases of asphalt paving will be 7:00 PM to 6:00 AM.

You can expect the following construction work hours and traffic restrictions:

  • Normal work hours for the contractor will be 7:00 AM to 4:00 PM.
  • Denny Way : All lanes will be open from 6:00 AM to 9:00 AM and 3:00 PM to 6:00 PM Monday through Friday. Traffic may be reduced to one lane in each direction at other times. We expect significant traffic impacts in this area and motorists are encouraged to use alternate routes.
  • Dexter Avenue N : All lanes of traffic will be open at all times with the exception of The hours for both phases of asphalt paving will bethe paving periods on Denny Way . Lane closures and parking restrictions on Dexter will begin this Friday at 7:00 PM and extend until the paving operations are completed on Saturday afternoon.

Construction Update: July 9, 2007

The Denny/Dexter/Mercer Street Paving project began on April 23, 2007 . Funding is provided by the “Bridging the Gap” transportation funding package approved by voters in November 2006. Here is an update on the project’s schedule:

Dexter Avenue N (Denny Way to Mercer Street )

  • Only minor clean-up and restoration remains. This work will be completed by the end of next this week.

Mercer Street ( Queen Anne Avenue N to 5 th Avenue N )

  • Final asphalt paving has been completed.
  • Pavement marking s are scheduled to be installed work is scheduled to take place by next week.

Denny Way ( 1 st Avenue N to 9 th Avenue N )

  • Curb ramp/sidewalk work is continuing and will be completed next this week.
  • Work is underway on repair of the roadway base, installation of traffic signal detector loops, and adjustments to utility (manhole) castings. This work is scheduled for completion by the middle of next week.
  • Asphalt paving of the roadway will take place in two phases : .
    • Phase 1- The first phase (Denny Way from 1 st Avenue N to 6 th Avenue N ) is scheduled for night work Friday, July 13 and day work Saturday, July 14. This work is weather dependent will be nighttime, weekend work, and depend on weather conditions .
    • Phase 2 - The second phase (Denny Way from 6 th Avenue N to Westlake/9 th Avenue N) is scheduled to take place at night the week of between July 1 5 6 and - July 19 20 . This will be nighttime, weekday work, and depend on work is weather conditions dependent .
  • Night work hours are The hours for both phases of asphalt paving will be 7:00 PM to 6:00 AM.

You can expect the following construction work hours and traffic restrictions:

  • Normal work hours for the contractor will be 7:00 AM to 4:00 PM.
  • Mercer St : All lanes will be open from 2:00 PM to 6:00 PM Monday through Saturday. Traffic may be reduced to one lane at other times.
  • Denny Way : All lanes will be open from 6:00 AM to 9:00 AM and 3:00 PM to 6:00 PM Monday through Friday. Traffic may be reduced to one lane in each direction at other times. We expect significant traffic impacts in this area and motorists are encouraged to use alternate routes.
  • On-street parking will be prohibited as needed to perform construction work in a safe and efficient manner.



Construction Update: June 14, 2007

Update on the Denny Way/Dexter Avenue N/ Mercer Street Paving Project

Dexter Avenue N (Denny Way to Mercer Street )

  • Additional concrete panel replacement has been necessary over the waterline north of Harrison Street. This work will be completed by the end of next week.
  • Clean-up, restoration, and final pavement markings will be completed before the end of June. The final pavement markings will include improvements to the bike lane throughout the project area.

Mercer Street ( Queen Anne Avenue N to 5 th Avenue N )

  • Weather permitting, final asphalt paving is scheduled for NIGHT TIME – Friday, June 15th beginning at 7:00 PM and continuing throughout the day on Saturday, June 16th. All on-street parking will be prohibited during this work.
  • If weather conditions prevent paving on Friday night, the work will be rescheduled for the following weekend.

Denny Way ( 1 st Avenue N to 9 th Avenue N)

  • Curb ramp/sidewalk work is scheduled to begin next week (Monday, June 18th).
  • The contractor also plans to begin repair of the roadway base next week.
  • Some weekend work will be necessary throughout this phase. Advanced notices will be provided.
  • Pavement grinding will take place for three (3) days AT NIGHT, the week of June 25th – 29th from the hours of 7:00 PM to 6:00 AM.

You can expect the following construction work hours and traffic restrictions:

  • Normal work hours for the contractor will be 7:00 AM to 4:00 PM.
  • Dexter Ave N : All southbound lanes will be open during the morning peak and all northbound lanes will be open during the afternoon peak periods. Traffic may be reduced to one lane in each direction at other times.
  • Mercer St : All lanes will be open from 2:00 PM to 6:00 PM Monday through Saturday. Traffic may be reduced to one lane at other times.
  • Denny Way : All lanes will be open from 6:00 AM to 9:00 AM and 3:00 PM to 6:00 PM Monday through Friday. Traffic may be reduced to one lane in each direction at other times. We expect significant traffic impacts in this area and motorists are encouraged to use alternate routes.
  • On-street parking will be prohibited as needed to perform construction work in a safe and efficient manner.
  • Business access will be maintained
  • Bicyclist traffic may have to merge with vehicular traffic. Appropriate signs will be posted.


Construction Update: June 1, 2007
Paving on Mercer, Dexter, Denny
Construction to begin Monday on Mercer Street


On Monday June 4, SDOTs contractor will begin street improvements on Mercer Street bordering Seattle Center, between Queen Anne Avenue N and Fifth Avenue N. All lanes on Mercer Street will be open from 2 to 6 pm Monday through Saturday. Traffic may be reduced to one lane at other times. On-street parking will be restricted

Daytime work will start with work on sidewalks and curb ramps, and also some concrete pavement repair. To avoid conflicts with a major Seattle Center event, the contractor will grind off the old asphalt roadway surface on Monday and Tuesday nights, from 7 p.m. to 6 a.m.

For two weeks the contractor will prepare Mercer Street for final asphalt paving. Final paving is scheduled to begin, weather permitting, Friday, June 15, from 7 p.m. and to continue though the night and into the following day, Saturday, June 16.

The contractor has completed laying new asphalt on Dexter Avenue North from Denny Way to Mercer Street. Finishing work will continue the next few weeks. Final pavement markings will include improvements to the bike lane throughout the Dexter project area. All southbound lanes of Dexter will be open during morning peak periods, and all northbound lanes will be open for afternoon peak periods; at other times traffic on Dexter may be reduced to one lane in each direction.

The contractor plans to begin work on Denny Way between First Avenue N and Ninth Avenue N in mid June.
Construction Update: May 17, 2007
Update on the Denny Way/Dexter Avenue N/Mercer Street Paving Project

The Denny/Dexter/Mercer Street Paving project began on April 23, 2007. Funding is provided by the "Bridging the Gap" transportation funding package approved by voters in November 2006. Here is an update on the project's schedule:

Dexter Avenue N (Denny Way to Mercer Street)
  • Curb ramp/sidewalk work is complete with the exception of the intersection of Harrison and Denny.
  • Pavement base repair and concrete panel replacement will be completed by the end of May. Significant panel replacement is necessary at the intersection of Harrison due to the water main break.
  • Installation of traffic detectors for signals and utility manhole adjustments will be completed next week.
  • Asphalt paving is scheduled for NIGHT WORK May 31st (weather permitting).
Mercer Street (Queen Anne Avenue N to 5th Avenue N)
  • Work will begin on Tuesday, May 29th.
  • Curb ramp/sidewalk work is the first scheduled activity. Concrete pavement repair will start a day after the curb ramp/sidewalk work begins.
  • Pavement grinding work is scheduled for June 6th and June 7th. This work will be performed at night.
Denny Way (1st Avenue N to 9th Avenue N)
  • Work scheduled to begin in mid-June
You can expect the following construction work hours and traffic restrictions:
  • Normal work hours for the contractor will be 7:00 AM to 4:00 PM.
  • Dexter Ave N: Traffic will be reduced to one lane in each direction at all times until final paving is complete at the end of May. Due to the additional concrete panel replacement at Harrison we are not able to open additional lanes during peak periods. Traffic delays are expected.
  • Mercer St: All lanes will be open from 2:00 PM to 6:00 PM Monday through Saturday. Traffic may be reduced to one lane at other times.
  • On-street parking will be prohibited as needed to perform construction work in a safe and efficient manner.
  • Business access will be maintained
  • Bicyclist traffic may have to merge with vehicular traffic. Appropriate signs will be posted.

Construction Update: May 4, 2007

Dexter Avenue N (Denny Way to Mercer Street )

  • Asphalt pavement grinding was completed May 3rd
  • Curb ramp/sidewalk work is ongoing and expected to be completed next week.
  • Pavement base repair and concrete panel replacement has begun and will be completed the week of May 14th.
  • Additional water main repairs are necessary as a result of the April 25th break. This work will take place the weekend of May 12th and be completed early the following week. SPU will distribute additional information to affected businesses.
  • Installation of traffic detectors for signals and utility manhole adjustments will begin next week, and be completed prior to final paving.
  • Final paving is expected the week of May 21st - 25th, weather permitting. Paving is tentatively scheduled to be completed at night.

Mercer Street ( Queen Anne Avenue N to 5th Avenue N )

  • Work could begin as soon as May 14th
  • Curb ramp/sidewalk work is the first scheduled activity
  • Pavement grinding work is scheduled for late May. This work will be performed at night.

Denny Way ( 1st Avenue N to 9th Avenue N )

  • Work scheduled to begin in mid-June

You can expect the following construction work hours and traffic restrictions:

  • Normal work hours for the contractor will be 7:00 AM to 4:00 PM.
  • Dexter Ave N (Southbound) : All lanes will be open from 6:00 AM to 9:00 AM , Monday through Friday. Traffic may be reduced to one lane in each direction at other times.
  • Dexter Avenue N (Northbound) : All lanes will be open from 4:00 PM to 6:00 PM Monday through Friday. Traffic may be reduced to one lane in each direction at other times.
  • Mercer St : All lanes will be open from 2:00 PM to 6:00 PM Monday through Saturday. Traffic may be reduced to one lane at other times.
  • On-street parking will be prohibited as needed to perform construction work in a safe and efficient manner.
  • Business access will be maintained
  • Bicyclist traffic may have to merge with vehicular traffic. Appropriate signs will be posted.
Project Description:

This project will improve the pavement condition along the arterials as outlined below and will improve accessibility by upgrading existing and installing new curb ramps to meet current standards. In general, the paving will involve grinding the top two inches of the asphalt surface, repairing the concrete base pavement where needed, and then re-paving with a two-inch asphalt overlay. Some concrete panel replacement will also be necessary.

Tentative Schedule by Location:

Work on Denny, Dexter and Mercer will not be simultaneous, save for brief overlaps with Dexter/Mercer and Mercer/Denny. Each phase slightly overlaps with the next. Weather conditions could impact the schedule.
  • Dexter - April 23, 2007 to late May 2007
  • Mercer - mid May 2007 to late June 2007
  • Denny - mid June 2007 to mid September 2007

Traffic Restrictions/Impacts:

Generally, all travel lanes will be open during the morning and afternoon peak periods. At other times, traffic may be reduced to one lane in each direction. Delays during these times are expected.

Denny Way: All travel lanes will be open from 6am-9am and 3pm-6pm Monday through Friday. Traffic may be reduced to one lane in each direction at other times.

Dexter Ave N (Southbound): All lanes will be open from 6am- 9am Monday through Friday. Traffic may be reduced to one lane at other times.

Dexter Ave N (Northbound): All lanes will be open from 4pm- 6pm Monday through Friday. Traffic may be reduced to one lane at other times.

Mercer Street: All lanes will be open from 2pm-6pm Monday through Saturday. Traffic may be reduced to one lane at other times.

Parking will be prohibited as needed to complete the construction work. Weekly construction notices may contain more detailed information about parking restrictions.

Special accommodations have been made in the construction contract to prohibit lane closures during major area events. Details will be provided in future notices.

Construction Notices:

SDOT will distribute notices with updated information as needed during the project. Notices will focus primarily on specific work areas and will be distributed almost weekly. A broader schedule update will be distributed approximately once per month. For more information, please contact either of the following:

George Frost
Public Outreach Coordinator
615-0786
george.frost@seattle.gov

Jessica Murphy, P.E.,
SDOT Project Manager
684-0178
jessica.murphy@seattle.gov



Subscribe to E-Mail Alerts

Denny, Dexter, and Mercer Paving List

E-mail:  

Subscribe (Join the list)

Unsubscribe (Remove me from the list)

  
Home | About Us | Contact Us | Site Index | News | FAQs | E-Mail Alerts