Seattle.gov Home Page
Seattle.gov This Department
Link to Transportation Home Page Link to Transportation Home Page Link to Transportation About Us Page Link to Transportation Contact Us Page
A vibrant Seattle through transportation excellence Peter Hahn, Director

Services 

Projects 

Planning 

Resources 

Events

News

Site Index


Bridging the Gap Home
Pedestrian Program Home
Sidewalk Development Program Home
15th Ave NE
Sand Point Way NE
1st Ave NE
Frequently-Asked Questions

1st Ave NE

Construction Update - 10/13/10

The curb and sidewalk are now complete. The contractor will next begin landscaping by installing tree root barrier, soil, hydroseed and trees. The project is expected to be substantially complete by October 22nd, with several more days to complete landscaping.

Construction Update – 9/16/10

The new walls are now under construction. Grading for the sidewalk and curb will begin soon, followed by paving of sidewalk and driveways. Impacts to your driveway access during construction will be minimized, but will be necessary at times.

Construction Update – 9/8/10

The contractor is performing utility work this week, including installing drainage structures. Grading for the new walls will begin soon. The first segment of new sidewalk may be constructed towards the end of the week of 9/13. *Please do not walk or bike on the new sidewalk until it is officially open*

Construction Update - 8/19/10

The contractor expects to start work at these locations the week of August 30th. You may see some initial set-up start on August 27th. Initial work this first week includes saw-cutting the existing pavement, removing vegetation and pavement within the project area. Next the contractor will install the drainage elements of the project and complete adjustments to utilities.

SDOT’s Sidewalk Development Program is making a significant pedestrian improvement on 1st Ave nue NE this year.  This project was selected using Seattle’s recently-adopted Pedestrian Master Plan and will fill in two gaps that are currently missing along the existing sidewalk.  Once completed, pedestrians will have a seamless facility to walk on that connects from NE 92 nd Street all the way to Northgate Mall.

The sidewalk project will be built along the east side of 1st Ave NE between the I-5 overpass (NE 92 nd Street) and Marie Callender’s Restaurant & Bakery at 9538 1st Ave NE.  SDOT’s preliminary design includes a 6’ wide concrete sidewalk with a planting strip and 6”curb.   

Construction is expected to begin in August.    A program representative will be in contact with adjacent residents and property managers with more details about the project prior to beginning this work.

PRELIMINARY DESIGN

If you would like more information about SDOT’s 2010 Sidewalk Development Projects, please contact Doug Cox at douglas.cox@seattle.gov