Construction Update 2/29/12:
Project status
- The new sidewalk has been constructed and is now open to pedestrians
- Trees are being planted next to the sidewalk in some locations this week
Construction Update 2/22/12:
Project status
- Sidewalk and driveway construction has been completed
- Tree planting and landscape work is now underway
What's ahead
- Additional landscaping and top soil work scheduled for next week
Construction Update 2/15/12:
Project status
- Sidewalk construction is underway between Evanston Avenue North and North Park Avenue North and should be finished this week, weather permitting
What's ahead
- Work to prepare the area between the new sidewalk and the roadway is scheduled for next week
Construction Update 2/8/12:
Project status
- Sidewalk construction is underway between Dayton Avenue North and Fremont Avenue North
What's ahead
- Work on the NW corner of North 125th Street and Greenwood Avenue North schedule to begin next week
- Sidewalk construction scheduled to begin next week between Fremont Avenue North and North Park Avenue North
Construction Update 2/1/12:
Project status
- Sidewalk and driveway construction is complete between Greenwood Avenue North and Phinney Avenue North.
- Sidewalk construction underway between Phinney Avenue North and Dayton Avenue North.
What's ahead
- Sidewalk construction between and Dayton Avenue North and Evanston Avenue North.
- Curb ramp construction at the southeast corner of Greenwood Avenue North and North 125th Street. Note: pedestrians may be detoured around the work zone.
Construction Update 1/25/12:
Project status
- Work has started again after delay due to snow.
- Sidewalk and driveway construction nearing completion between Greenwood Avenue North and Phinney Avenue North.
What's ahead
- Sidewalk construction between Phinney Avenue North and Dayton Avenue North. Note: pedestrians may be detoured around the work zone.
Construction Update 1/18/12:
Project status
- Storm drainage items have been installed.
- Sidewalk construction between Greenwood Avenue North and Phinney Avenue North has been completed.
- Progress has been slowed due to snow
What's ahead
- Sidewalk and driveway construction will continue once snow melts
Construction Update 1/11/12:
Project status
- Area for the new sidewalk is being prepared for construction.
- Trees and hedges have been cleared out of the way.
- Storm drainage items are being installed.
What's ahead
- Sidewalk construction will begin between Greenwood Avenue North and Phinney Avenue North. Note: pedestrians may be detoured around the work zone.
- Driveway construction will begin. Note: short-term driveway restrictions will be in place.
Construction Update 12/21/11
SDOT and its contractor will mobilize and start work activity on or shortly after January 3, 2012. This project is scheduled to be complete by early March.
Normal work hours will be 7:00 a.m. – 6:00 p.m., Monday through Friday. Parking restrictions in and around the work zone should be expected.
For questions regarding construction, please contact James Sido, Community Communications Officer, james@stephersonassociates.com, (206) 972-6198 |