Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
Link to Transportation Home Page Link to Transportation Home Page Link to Transportation About Us Page Link to Transportation Contact Us Page
Delivering a first-rate transportation system for Seattle Scott Kubly, Director

Services 

Projects 

Planning 

Resources 

Events

News

Site Index

47th Avenue SW and SW Admiral Way Signal

Update: May 5, 2015

Construction Updates

Construction to stop for approximately three weeks

Crews are wrapping up work this week with remaining asphalt paving and laying topsoil. As we’ve mentioned, construction will stop this week until we receive equipment for the new signal. Pedestrian and bicycle access will be fully restored during this time and no lane restrictions will be in effect as part of this project. Users of the area can expect to see construction cones covering the signal pole foundations at the corners. The overhead pedestrian signal will remain in place until crews are able to install the new traffic signal. We anticipate construction will resume in approximately three weeks, at the end of May, depending on delivery of the signal equipment.
After the signal equipment is received, crews will:

  • Install signal equipment including poles and mast arms, signal heads and cabinets
  • Stripe the intersection with new crosswalks and a new left-turn pocket on SW Admiral Way
  • Remove the existing overhead pedestrian signal
  • Complete remaining landscaping

Outreach

We are committed to keeping the community informed and will distribute an update approximately one week before work at the intersection resumes. When construction resumes, residents, businesses and travelers can expect the following impacts:

  • Construction activity from 7 AM – 3 PM
  • Pedestrian and bicycle detours around work areas
  • Temporary lane and parking restrictions during of-peak travel times on 47th Avenue SW, SW Admiral Way and SW Waite Street
  • Noise, dust and vibration associated with concrete removal and paving

Click here to sign up for project email updates. 

Questions?

If you have questions or concerns, you can contact the construction outreach lead, Rachel McCaffrey at rachel.mccaffrey@seattle.gov or 206-615-0925.

 

 

Project Description

The Seattle Department of Transportation (SDOT) is planning a project to improve the three-way intersection of 47th Avenue SW, SW Admiral Way and SW Waite Street for people walking, biking and driving. SDOT will install a new signal and additional crosswalks at this intersection to help improve the flow of traffic.

Project Elements

The project will include

  • Installing a new traffic signal
  • Adding four additional striped crosswalks
  • Upgrading six curb ramps at key corners of the intersection to be compliant with current American Disability Act (ADA) standards
  • Replacing the existing center-turn lane with left-turn-only pockets on SW Admiral Way
  • Removing minimal parking up to 50 feet from the intersection approaches on the north and south sides of 47th Avenue SW and SW Waite Street
  • Removing the existing pedestrian signal

Project Schedule and Impacts

Project design was completed in late 2014. Construction is scheduled to begin in the spring of 2015 and will last for approximately 12 weeks, depending on weather conditions.

During construction, the following impacts can be expected:

  • Temporary parking and lane restrictions on 47th Avenue SW, SW Admiral Way and SW Waite Street
  • Pedestrian and bicycle detours around the work areas
  • Noise, dust and vibration associated with concrete removal and paving
  • Construction activity during normal work hours, from 7 AM – 6 PM

Project Outreach

SDOT is committed to engaging with the community and understanding needs in the project area. The project team will keep the community informed as the project approaches the start of construction.

Previous

February 11, 2014

Briefing to the Admiral Neighborhood Association

August 11, 2014

Project introduction letter to property owners in surrounding area

September 9, 2014

Briefing to the Admiral Neighborhood Association

February 10, 2015 Briefing to the Admiral Neighborhood Association
March 3, 2015 Construction notification postcard to surrounding area

 

Funding

This project is funded the Seattle’s Carpool Parking Tax and the Bridging the Gap (BTG) transportation levy, passed by voters in November 2006 and scheduled to expire in 2015.

Contact Us

If you have questions about this project please contact Maribel Cruz at maribel.cruz@seattle.gov or 206-684-7963.

If you need this information translated, please call 206-615-0925.

如果您需要把下列資訊翻譯成中文,請致電206-615-0925.

Si usted necesita esta información traducida al español por favor llame al 206-615-0925.

Kung kailangan ninyong isalin sa Tagalog ang impormasyong ito, paki-tawag lang sa206-615-0925.

Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt, xin gọi số 206-615-0925.

Home | About Us | Contact Us | Site Index | News | FAQs | E-Mail Alerts