2006 Construction Projects List See what we did last year! Resurfacing | Pedestrian Improvements | Bicycle Improvements | Arterial Safety Improvements | Roadway Structures | Traffic Signals | Capital Projects | Traffic Circles/Calming Each year, the City of Seattle allocates funds for arterial paving and resurfacing. The Seattle Department of Transportation (SDOT) manages this and other street maintenance programs. SDOT also monitors the conditions of city streets and selects the streets to be paved.The larger part of the arterial paving funds is used for work bid out to private contractors. In addition to the work performed by private contractors, SDOT's own street-paving crews perform small spot-paving projects on arterial streets. In addition to the streets included in Seattle Department of Transportation's annual paving program, some streets are paved as part of projects that include general street improvements. South Henderson Street Improvements Improve access and mobility for pedestrians, transit, bicyclists, freight and vehicles. Street improvements focus on pedestrian safety. Planting strips and street trees between the sidewalk and the roadway are added by relocating the curb and gutter. Curb bulbs are installed at key pedestrian crossings. Other street improvements include widening the existing sidewalk, repairing pavement base, repairing existing bus layover areas, and installing new pedestrian lighting. The improvements to South Henderson Street will connect the Henderson Street light rail station with the Rainier Beach commercial area.Construction Scheduled to Begin: Summer 2006 Estimated Construction Cost: $700,000 Contact: Diana Holloway 15th Avenue NE from NE 125th Street to NE 145th Street * This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades. Construction Scheduled to Begin: Fall 2005 Contact: Trevor Partap Pinehurst Way NE from Roosevelt Way NE to NE 117TH ST * This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Spring 2006 Contact: Trevor Partap Roosevelt Way NE from NE 92nd Street to NE Northgate Way * This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Spring 2006 Contact: Trevor Partap Northgate Way NE from 5th Avenue NE to 15th Avenue NE * This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Spring 2006 Contact: Trevor Partap * Estimated Constuction Cost for all four projects: $1,941,000 Queen Anne Avenue N from Harrison Street to Roy Street † This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Spring 2006 Contact: Trevor Partap 1st Avenue N from Denny Way to Roy Street † This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Spring 2006 Contact: Trevor Partap Roy Street from Queen Anne Avenue N to 5th Ave N † This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Spring 2006 Contact: Trevor Partap 10th Avenue W from W Crockett Street to W Bothwell Street † This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Scheduled to Begin Construction: Summer 2005 Contact: Trevor Partap † Estimated Constuction Cost for all four projects: $2,578,000 N/NE 45 Street from N Midvale Place to 15th Avenue NE § This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Summer 2006 Contact: Jessica Murphy NE 45 Street from Sand Point Way NE to 43rd Avenue NE § This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Summer 2006 Contact: Jessica Murphy 15th Avenue NE from NE 45 Street to NE 55 Street § This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Summer 2006 Contact: Jessica Murphy § Estimated Construction Cost for all three projects: $2,458,000 California Avenue SW from SW Edmunds Street to SW Admiral Way SW ± This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Summer 2006 Contact: Jessica Murphy Admiral Way SW from California Avenue SW to SW Olga Street ± This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Construction Scheduled to Begin: Summer 2006 Contact: Jessica Murphy ± Estimated Construction Cost for both projects: $3,092,000 S Jackson Street from 14th Avenue S to MLK Jr.Way S This project is part of the Seattle Department of Transportation's Arterial Asphalt and Concrete Program and includes asphalt resurfacing, placement of loop detectors for signals, street trees, and wheelchair curb ramp upgrades.Estimated Construction Cost: $598,000 Construction Scheduled to Begin: Spring 2006 Contact: George Frost Chip seal in the Northgate area, east of I-5 Chip seal is an extremely cost efficient road surfacing product that economically provides a skid-resistant surface for almost one quarter of Seattle's nonarterial streets. After streets are repaired, an asphalt emulsion is applied immediately followed by layer of chipped rock.Estimated Construction Cost: Summer 2006 Construction Scheduled to Begin: July, 2006 Contact: Susan Almachar Magnolia Blvd W, from 29th Ave W to W Garfield St This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, and wheelchair curb ramp upgrades.Estimated Construction Cost: $100,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts South side of E Pine St, from Boylston Ave to Nagle Place This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $60,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts 3rd Ave W, from W McGraw St to W Raye St This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $60,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts East side of Eastlake Ave E, from Harvard Ave E to Fuhrman Ave E This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $42,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts West side of 15th Ave E, from E Madison St to E Denny St This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $80,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts S Holden Street, from 5th Ave S to 200 feet west of 5th Ave S This project is an SDOT Crew Arterial Major Maintenance Project that includes a major asphalt pavement spot repair.Estimated Construction Cost: $55,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts NE 71st ST, Green Lake Dr N to 6th Ave NE This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $100,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts Center median of NW Market St, from 15th Ave NW to 9th Ave NW This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $100,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts Lenora St, from 3rd Ave to 5th Ave This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $76,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts Yesler Way, from 1st Ave to 3rd Ave This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $84,000 Construction Scheduled to Begin: Spring 2006 Contact: Paul Roberts 3rd Ave, from Yesler Way to S Washington St This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $70,000 Construction Scheduled to Begin: Spring 2006 Contact: Paul Roberts Corson Ave S, from S Dorris St to Airport Wy S This project is an SDOT Crew Arterial Major Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $65,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts NE 41st St, from Brooklyn Ave NE to 15th Ave NE This project is an SDOT Crew Non-Arterial Maintenance Project that includes asphalt resurfacing and wheelchair curb ramp upgrades.Estimated Construction Cost: $58,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts 18th Ave, from E Jefferson St to E Cherry St This project is an SDOT Crew Non-Arterial Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $75,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts Bell St, from 2nd Ave to 4th Ave This project is an SDOT Crew Non-Arterial Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $80,000 Construction Scheduled to Begin: Summer 2006 Contact: Paul Roberts Russell Ave NW, from 20th Ave NW to NW Market St This project is an SDOT Crew Non-Arterial Maintenance Project that includes asphalt resurfacing, placement of loop detectors for signals, and wheelchair curb ramp upgrades.Estimated Construction Cost: $45,000 Construction Scheduled to Begin: Spring 2006 Contact: Paul Roberts Hiram Pl NE, from NE 120th St to Lake City Wy NE This project is an SDOT Crew Non-Arterial Maintenance Project that includes asphalt resurfacing.Estimated Construction Cost: $28,000 Construction Scheduled to Begin: Spring 2006 Contact: Paul Roberts Lorentz Pl N, from McGraw Pl to the Dead End This project is an SDOT Crew Non-Arterial Maintenance Project that includes asphalt resurfacing and wheelchair curb ramp upgrades.Estimated Construction Cost: $37,000 Construction Scheduled to Begin: Spring 2006 Contact: Paul Roberts. Shilshole Shoulder Improvement Perform maintenance work to the southwest side of Shilshole Ave NW from the Ballard Bridge to 24th Ave NWEstimated Construction Cost: $50,000 Construction Scheduled to Begin: Spring 2006 Contact: Paul Roberts Pedestrian Improvements and Maintenance 16th Avenue South between South Dakota Street and South Nevada Street Install new sidewalk by Asa Mercer SchoolEstimated Construction Cost: $60,000 Construction Scheduled to Begin: Early May Contact: Trung Pham NW 44th Street between Baker NW and 3rd Ave NW Install new sidewalk to fill in missing link leading to Ross Park, and add street treesEstimated Construction Cost: $45,000 Construction Scheduled to Begin: Late Spring 2006 Contact: Trung Pham 3rd Avenue W between W Newell Street and W Armor Street Build new sidewalk to fill in missing link leading to David Rogers playfield Estimated Construction Cost: $70,000 Construction Scheduled to Begin: Late Summer 2006 Contact: Trung Pham NE 98th Street between Lake City Way NE and NE 20th Ave Install new asphalt walkway with concrete curbEstimated Construction Cost: $225,000 Construction Scheduled to Begin: Fall 2006 Contact: Ron Scharf Dayton Ave N from N 86th Place to N 87th St Install new asphalt walkway with extruded concrete curbEstimated Construction Cost: $70,000 Construction Scheduled to Begin: Summer 2006 Contact: Shauna Walgren Improve sidewalk between NE 35th and NE 39th Street, south side. Estimated Construction Cost: $100,000 Construction Scheduled to Begin: TBD 2006 Contact: Shauna Walgren 15th Ave NE from NE 92nd St to NE 96th St Install new sidewalkEstimated Construction Cost: $90,000 Construction Scheduled to Begin: TBD 2006 Contact: Shauna Walgren NE 130th St between 30 Ave NE and 31 Ave NE (North Side) Install new asphalt walkway with extruded concrete curbEstimated Construction Cost: $53,000 Construction Scheduled to Begin: Summer 2006 Contact: Theresa Smith N 100th St between Densmore Ave N and Wallingford Ave N (North Side) Install new asphalt walkway with extruded concrete curbEstimated Construction Cost: $90,000 Construction Scheduled to Begin: Complete Contact: Theresa Smith S Garden St between Rainier Ave S and S Orchard St Install extruded concrete curb and planting strip to improve existing sidewalkEstimated Construction Cost: $126,000 Construction Scheduled to Begin: Summer/Fall 2006 Contact: Theresa Smith 30th Ave NE Sidewalk Improvement Install new sidewalk on 30th Ave NE from NE 55th Street to BlakelyEstimated Construction Cost: $118,500 Construction Scheduled to Begin: TBD 2006 Contact: Shauna Walgren 37th Ave S between S Dawson St and S Hudson St (East Side) Install extruded concrete curb and planting strip to improve existing sidewalkEstimated Construction Cost: $70,000 Construction Scheduled to Begin: Summer/Fall 2006 Contact: Theresa Smith NE 120th St between 30 Ave NE and 31 Ave NE Install new asphalt walkway with extruded concrete curbEstimated Construction Cost: $32,000 Construction Scheduled to Begin: Spring 2006 Contact: Jessica Murphy S Henderson between 7th Ave S and 8th Ave S (South Side) Install extruded concrete curb and planting strip to improve existing sidewalkEstimated Construction Cost: $75,000 Construction Scheduled to Begin: Summer/Fall 2006 Contact: Theresa Smith 4th Avenue S. Curb/Planting Strip Install new curb and planting strip on 4th Avenue South from S Michigan St to S Dawson StEstimated Construction Cost: $148,000 Construction Scheduled to Begin: 2007 Contact: Shauna Walgren Install new curb bulbs at 31st Ave S and S Lane Estimated Construction Cost: $44,000 Construction Scheduled to Begin: Summer 2006/Fall 2006 Contact: Sivaraman Balachandran Install new curb bulbs at NE 56th St and Latona Ave NE Estimated Construction Cost: $44,000 Construction Scheduled to Begin: Summer/Fall 2006 Contact: Eric Teegarden Curb Ramps Add approximately 200 curb ramps at multiple locations.Estimated Construction Cost: $300,000 Construction Scheduled to Begin: Spring through fall Contact: Pete Lagerwey Pedestrian Crossing Improvements Improve street crossings at approximately 60 locations.Estimated Construction Cost: Construction Scheduled to Begin: Spring through fall Contact: Pete Lagerwey Curb Bulb and Sidewalk Improvements Install pedestrian improvements at various locations in Seattle. Locations will be determined in May, 2006.Estimated Construction Cost: Construction Scheduled to Begin: Contact: Pete Lagerwey 15th and Holman Road
N. 45th Pedestrian Crossing and Sidewalk Rehabilitate pedestrian crosswalks and sidewalks on N 45th Street in conjunction with the asphalt resurfacing project.Estimated Construction Cost: $110,500 Construction scheduled to Begin: April 2006 Contact: Trevor Partap Ballard/Vernon/Market Sidewalk Rehabilitate one block-face of existing sidewalk on Ballard Ave.Estimated Construction Cost: $75,000 Construction scheduled to Begin: Summer 2006 Contact: Paul Roberts Belltown Sidewalk Improvements Rehabilitate existing sidewalks at locations throughout Belltown Estimated Construction Cost: $39,000 Construction scheduled to Begin: Summer 2006 Contact: Susan Almachar Broadway Sidewalk Rehabilitation Rehabilitate existing sidewalks at Broadway and Spruce StreetEstimated Construction Cost: $38,000 Construction scheduled to Begin: Summer 2006 Contact: Susan Almachar California Ave SW Sidewalk Rehab Rehabilitate existing sidewalks at California Avenue SW and Admiral WayEstimated Construction Cost: $73,000 Construction scheduled to Begin: Summer 2006 Contact: Susan Almachar Rehabilitate existing sidewalks in the 700 block of East Pine Street and the 1100 block of East Pine Street Estimated Construction Cost: $70,000 Construction scheduled to Begin: Summer 2006 Contact: Susan Almachar Queen Anne Sidewalk Rehabilitation Rehabilitate existing sidewalks on Queen Anne Avenue N, Galer Street, and McGraw StreetEstimated Construction Cost: $54,000 Construction scheduled to Begin: Summer 2006 Contact: Susan Almachar Rehabilitate existing sidewalks on 1st Ave S from Blancard to Bell Tower Estimated Construction Cost: $39,000 Construction scheduled to Begin: TBD 2006 Contact: Shauna Walgren Rehabilitate existing sidewalks on 35th Ave NW from NW 96th Street to NW 97th Street Estimated Construction Cost: Construction scheduled to Begin: Summer 2006 Contact: Susan Almachar Eastlake Pedestrian Walkway Improvement Perform maintenance work to existing walkway on E Louisa Street from Eastlake Ave E to Yale Ave E.Estimated Construction Cost: $3,500 Construction Scheduled to Begin: Summer 2006 Contact: Liz Ellis Pioneer Square Sidewalk Rehabilitation Estimated Construction Cost: $20,000Construction Scheduled to Begin: TBD 2006 Contact: Shauna Walgren Bicycle Improvements and Pedestrian/Bike Trails SDOT's Bicycle Program has been working steadily toward developing an urban trail system to accommodate bicyclists. Urban trails include shared use paths, bike lanes, signed bike routes, arterials with wide shoulders, and pedestrian pathways. The Bicycle Spot Improvement Program makes low cost improvements to the existing street system to enhance bicycle safety and convenience. Seattle's segment of this regional trail will run for approximately one mile in the City Light power line corridor just west of Evergreen-Washelli Cemetery between North 110th Street and 128th Street. Future improvements are planned for Linden Avenue to link the Seattle and Shoreline sections of the trail, including the installation of a traffic signal at Linden Avenue North and North 145th to facilitate pedestrian and bicycle crossings. There will also be trees and landscaping at two trail heads.Estimated Construction Cost: $963,700 Construction Scheduled to Begin: Completed Contact: Stuart Goldsmith Burke-Gilman Trail (to Golden Gardens; also, "link") Estimated Construction Cost: $2,682,000 Construction Scheduled to Begin: Completed Contact: Diana Holloway Burke Gilman Trail, Intersection of Seaview Ave NW and Seaview Pl NW Make pedestrian and vehicle safety improvements in this intersection which is the trailhead for Burke Gilman Trail.Estimated Construction Cost: $85,000 Construction Scheduled to Begin: Spring 2006 Contact: Diana Holloway This project will construct about 3/4 of a mile of multi-use trail along the south side of the Ship Canal beginning at 6th Ave W (where Phase 1 ends) and terminating at the Emerson St bike path directly under the Emerson St Viaduct just west of the BNSF right-of-way. This project constructs a critical missing link in Seattle's Urban Trails System. Once completed, the Ship Canal Trail will make it possible to bicycle from Redmond to downtown Seattle almost entirely on dedicated bicycle facilities. Estimated Construction Cost: $ 3 million Construction Scheduled to Begin: Spring 2007 Contact: Stuart Goldsmith This project will involve the construction of 3.6 miles of pedestrian/bicycle trail in southeast Seattle between Beacon Avenue South at South Dawson Street and 51st Avenue South at South Gazelle Street. Alignment is primarily beneath Seattle City Light transmission corridor. Estimated Construction Cost: $2,060,000 Construction Scheduled to Begin: Summer 2004 Contact: Connie Zimmerman This is a joint project between the City of Seattle and the Port of Seattle. With this project, the Port and the City will complete a missing link in the Duwamish Trail system between Chelan Avenue SW and SW Idaho Street. An off-road asphalt path will be constructed on the east side of West Marginal Way SW and connect to existing trail portions to the north and south. Portions of this project include extensive landscape improvements, trees and understory planting in planting strips. Estimated Construction Cost: $750,000 Construction Scheduled to Begin: Summer 2007 Contact: Ron Scharf Bike Spot 2006—SDOT will make minor repairs or improvements for bicyclists
at various locations throughout Seattle. The locations will be determined during
the year. Bike Racks: SDOT will replace approximately 200 bicycle racks at various
locations. Aurora Avenue and N 87th Street Install Median Channelization IslandEstimated Construction Cost: Construction scheduled to begin summer, 2006 Contact: Kristine Baldwin Aurora Avenue and N 88th Street Install Median Channelization IslandEstimated Construction Cost: Construction scheduled to begin summer, 2006 Contact: Kristine Baldwin The Seattle Department of Transportation operates and maintains over 150 bridges throughout Seattle, including four movable bridges. The SDOT Roadway Structures Division also builds and maintains retaining walls, stairways, seawalls and tunnels in Seattle. Fremont Bridge Approaches Replacement Replace existing bridge approach structures. Install traffic improvements to mitigate construction impacts. Upgrade mechanical-electrical components of the bridge. Minor landscape restoration.Estimated Construction Cost: $22,813,000 Construction Began: Summer 2005 Contact: Lorelei Mesic Widen the existing Spokane Viaduct on the north side by approximately 41 feet. Rebuild 1st Ave S and 4th Ave S ramps. Trees and other landscape improvements. Estimated Construction Cost: $128,000,000 Construction Scheduled to Begin: Pending Full Funding Contact: Stuart Goldsmith 2005 Pier Protection Repairs (University Bridge and South Spokane Street
Bridge) 2nd Avenue Extension Bridge--Bridge Painting 35th Ave NE and NE 110th Pedestrian Bridge 2nd Matthews Beach Pedestrian Bridge Retaining Wall Rehabilitation Program Stairway Rehabilitation Program Duwamish Intelligent Transportation System Westlake Ave. N. & Crockett St. - pedestrian signal Harvard Ave. & E. Pike St- full signal Greenwood Ave. N. & N. 90th St- full signal Boren Ave. & Union St. - upgrade of existing to full signal Barnes Ave. N.W. & N.W. Market St. - pedestrian signal 15th Ave. N.E. & N.E. 120th St- Pedestrian signal Linden Ave. N. & N. 145th St- full signal Fauntleroy Way S.W. @ Lincoln Park- pedestrian signal Delridge /SW Roxbury/16th Ave SW 35th Avenue NE/NE 65th Street and NE 75th Street Fifth Avenue Northeast Sidewalks (Northgate) Bridge Way North Street Improvements State Route 519, Phase One Surface Street Improvements Phinney Avenue North/Fremont Avenue North/ North 50th Street South Jackson Street Improvements Lake City Way NE Multimodal Phase One Greenwood Avenue N. and Holman Road N./ N. 105th Street Downtown Seattle Bus Layover Traffic Calming Devices (Traffic Circles and Speed Humps) 30th Ave SW & SW Cloverdale St 40th Ave SW & SW Manning Street 28th Ave NE, Hiram Pl NE, and NE 120th St 25th Ave S and S Dearborn St 26th Ave S and S Dearborn St 26th Ave S and S Judkins St 24th Ave S and S Norman St 29th Ave S and S Judkins St Woodlawn Park Ave N and N 36th St 22nd Ave E and E Republican St 39th Ave S between S Graham St and S Juneau St 10th Ave NE between NE 125th St and NE 135th St Speed
Humps (6) 32nd Ave NE and NE 123rd St 27th Ave NE and NE 72nd St 9th Ave NW and NW 49th St 30th Ave NW and NW 59th St 26th Ave S & S Dawson St 37th Ave SW and SW Cloverdale St 36th Ave SW and SW Hinds St 18th Ave and E Pike St 27th Ave and E Pine St Franklin Ave E and E Edgar St |
|