Rainier Beach Playfield Improvements
|
|||||||||
| LOCATION |
8802 Rainier Ave S, Seattle WA 98118
|
| BUDGET |
The Parks and Green Spaces Levy Maintenance Adjustment fund allocates:
Play Area Renovation: $300,000 Tennis Courts & Lighting Replacement: $1,300,000 |
| SCHEDULE |
Planning: April - June 2012
Design: July 2012 - May 2013
Construction: June- September 2013
Completion: September 2013
|
The play area renovation includes new play equipment for children ages 2-12, improved safety surfacing, better accessibility and site amenities that may include picnic tables and seating area. The tennis court renovation constructs new courts, adds new energy efficient lighting, and improves access.
Public Meeting #1 07/17/12
Public Meeting #2 08/18/12
*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.
No events are scheduled at this time.
Patrick Donohue, Project Manager
800 Maynard Ave S
Suite 300
Seattle, WA 98134
206-684-9286
patrick.Donohue@seattle.gov
|