Seattle.gov Home Page
Seattle.gov This Department
Seattle Parks and Recreation Seattle Parks and Recreation Home Page Seattle Parks and Recreation - About Us Seattle Parks and Recreation - Contact Us
Christopher Williams, Acting Superintendent.
  Parks   Centers & Pools Activities Reservations & Permits Projects & Planning A - Z Index
 
Parks Legacy Plan
Partnerships
Parks and Green Spaces Levy
Acquisition
Development
Environment
Opportunity Fund
Oversight Committee
Pro Parks Levy
Community Center Levy
Major Maintenance
Neighborhood Matching Fund
Horticulture
Sustainable Building & Development
City-Wide Planning Documents
Plans for Individual Parks
Parks Standards
Policies and Agreements
Requests for Proposals
Requests for Qualifications
Board of Park Commissioners
Seattle Parks Foundation
Seattle Conservation Corps
Parks Preservation Work Group
Seattle Parks and Recreation

Beacon Hill Playground Renovation
Parks and Green Spaces Levy
Project Information

 

Location: 1902 13th Ave S, Seattle WA 98144


Project Status

Thank you Seattle! This project is complete.
Parks removed construction fencing at the end of December 2010.

The construction contract for the project was awarded to RN Faulk. The project began in September 2010. This project provides site improvements to the play area at Beacon Hill Playground.


LOCATION
1902 13th Ave S, Seattle WA 98144
BUDGET
The Parks and Green Spaces Levy
provides $180,000 for planning, design
and construction.
SCHEDULE
Design: September 2009 - April 2010
Construction: September 2010 - November 2010
Completion: November 2010

Project Description

This project will provide access improvements and other site improvements at this existing play area. The scope of this project brings the play area into compliance with current play area safety standards and guideline efforts of the American Society of Testing and Materials (ASTM) and the Consumer Product Safety Commission (CPSC) as well as meets the requirements of the Americans with Disabilities Act (ADA).



Community Participation

Public Meeting #1 1/5/2010


Important Links


*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.

 
Updated January 4, 2011

Events

There are no events planned at this time.

For More Information

Kelly Davidson
800 Maynard Ave S,
Suite 300
Seattle, WA 98134
206-684-0998
kelly.davidson@seattle.gov

Schematic Design Plan
Schematic Design Plan
You will need adobe acrobat reader to view this document.

Select image to enlarge
 Home | Partnerships | Park Board | Volunteer | FAQ | Parkways Parkways Icon | Facebook Facebook Icon | @SeattleParks Twitter Icon | Flickr Flickr Icon