Major Maintenance Project Information
South Park Community Center Exterior Siding Replacement
Address:
8319 8th Ave S, Seattle 98108
Current Status
Thank you Seattle! This project is complete.
The damaged exterior panel siding of the South Park Community Center has been replaced.
S.M. Stemper Architects are the design consultant on the project. Construction is expected to take place in November 2011.
Project Description
Budget:
$200,000
Construction begins:
Summer 2011
Project complete:
Fall 2011
The project will provide design and construction for the replacement of exterior panel siding on the South Park Community Center. The existing siding is greatly damaged, allowing water to penetrate into the backing and insulation.
Community Involvement
*Note:
To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.
Updated
November 7, 2012
|