Seattle Aquarium / Pier 59 Remodel Project
Parks Project Manager: Colleen Browne (206) 684-4155 | colleen.browne@seattle.gov
Turner Construction Project Manager: Tim Charoni 206-571-2670
Remodeling of the Seattle
Aquarium
at Pier 59 began in June, 2005. Seattle Parks and Recreation has begun
restoring structural integrity to the majority of the facility by installing
new driven and posted piles and new concrete aprons (to replace existing
wooden ones).
» Project Update!
(Update: 4/17/06)
Safety Counts
The Seattle Aquarium remodeling project has completed over 70,000 hours
of work without a reportable safety incident! This is due to our wonderful
crews of workers, and to Turner Construction's diligent project oversight.
Project Schedule
|
| Construction Highlights |
Site mobilization
|
May 2005 |
| Replace aprons |
July '05 - Feb '06 |
| Remove east façade |
Sept. '05 |
| Drive pile in east end apron |
Oct. - Nov. '05 |
| New deck on east end |
Dec. '05 |
| New building structure |
Feb. - June '06 |
| Substantial completion |
06/20/06 |
| Physical completion |
09/13/06 |
| Note: Normal circumstances of construction
might change these dates. Changes will be posted. |