Major Maintenance Project Information
Basketball Lighting Improvement
Address:
4600 39th Ave. S Seattle, WA 98118
Current Status
October 2009
Planning and design for the Rainier courts is complete and Zinc Construction will begin installation of lighting on November 9, 2009. Seattle Parks held a public meeting in September 2009. Information from the meeting is below.
The Van Asselt court project timeline is still to be determined.
Project Description
Budget:
$175,000
Construction begins:
11/1/2009
Project complete:
3/1/2010
The Basketball Court Lighting project intends to provide planning, design and construction for new court lighting at two park locations: Rainier Playfield (2 courts) and Van Asselt Community Center (2 courts).
Community Involvement
Public Meeting
* Note: To view this document, you must have the Adobe Acrobat
Reader installed on your system. If you already have the Reader installed,
select the file above. If you don't have the Reader, you can get it
at the Adobe
web site for free.
Updated
October 14, 2009
|