Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
Seattle Parks and Recreation Seattle Parks and Recreation Home Page Seattle Parks and Recreation - About Us Seattle Parks and Recreation - Contact Us
Christopher Williams, Acting Superintendent.
  Parks   Centers & Pools Activities Reservations & Permits Projects & Planning A - Z Index
 
Parks Legacy Plan
Partnerships
Parks and Green Spaces Levy
Pro Parks Levy
Community Center Levy
Major Maintenance
Neighborhood Matching Fund
Horticulture
Sustainable Building & Development
City-Wide Planning Documents
Plans for Individual Parks
Parks Standards
Policies and Agreements
Requests for Proposals
Requests for Qualifications
Board of Park Commissioners
Seattle Conservation Corps
Parks Preservation Work Group
Seattle Parks and Recreation

Major Maintenance Project Information
Basketball Lighting Improvement

 

Address: 4600 39th Ave S Seattle, WA 98118


Current Status

November 2010
Thank you, Seattle! This project is complete.

The Rainier Basketball court lighting installation was completed in August 2010.

Project Description

Budget: $175,000
Construction begins: 3/1/2010
Project complete: 8/1/2010

The Basketball Court Lighting project intends to provide planning, design and construction for new court lighting at Rainier Playfield (2 courts).


Community Involvement


Public Meeting

*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.

 
Updated November 12, 2010

More Information

Kelly Davidson
800 Maynard Ave S
Suite 300
Seattle, WA 98134
206.684.0998
e-mail

Events

There are no events scheduled at this time.

Links

 Home | Partnerships | Park Board | Volunteer | FAQ | Parkways Parkways Icon | Facebook Facebook Icon | @SeattleParks Twitter Icon | Flickr Flickr Icon