Seattle Parks and Recreation crews removed the old play structure in July 2021 and the new play equipment was installed in October. In December, the contractor installed formwork for new accessible concrete ramps. The ramps will be installed after the concrete labor strike is resolved and material is available. In January, new drainage pipes and surfacing material will be installed. The play area will open by early February.

Location

Fairmount Playground, 5400 Fauntleroy Way SW, 98136

Budget

Seattle Park District provides $400,000 for planning, design and construction.

Schedule

Planning: Winter - Spring 2019
Design: Spring - Fall 2019
Construction: Fall 2021
Completion: Winter 2021/2022

Project Description

This project will replace the play equipment in the south play area, installed in 1996, and improve accessibility in compliance with the Americans with Disabilities Act (ADA). The play area will be closed during construction.

Community Participation

Public Meeting 5/30/2019