West Seattle Stadium Track Resurfacing Project

Updated: April 13, 2017

Spring 2017

Seattle Parks and Recreation hired DA Hogan as lead Design and Engineering Consultant. Surveying and surface coring is complete. This project is generated as a major maintenance facility priority.

During construction the stadium track will be closed. Seattle Parks and Recreation and the contractor hired for the project will work to minimize impact to the neighborhood.

Location

West Seattle Stadium, 4432 35th Ave. SW, Seattle, WA 98126

Budget

The Seattle Park District provides $950,000 for this major Seattle Parks and Recreation investment.

Schedule

Planning and Design: Winter 2016 - Spring 2017
Bidding: Spring 2017
Construction: Summer 2017
Completion: Late Summer 2017

Project Description

The project will replace and resurface the existing rubberized track.