Licton Springs Park Play Area Renovation

Updated: December 13, 2016

Thank you Seattle this project is complete!

Seattle Parks and Recreation appreciates the participation from the community in the public process and hope you enjoy the renovation and new play equipment.

Location

Licton Springs Park, 9536 Ashworth Ave N, 98103

Budget

The Seattle Park District provides $200,000 in funding for planning, design and construction.

Schedule

Planning: Fall 2015 - Winter 2016
Design: Spring 2013 - Spring 2016
Construction: Spring 2016 - Fall 2016
Completion:
Fall 2016

Project Description

Replace playground equipment which will include play elements and access for children of all ages and abilities.

Community Participation

Public Meeting 4/30/2016