Lakewood Playground Park Play Area Renovation

Updated: October 2, 2019

Fall 2019

Seattle Parks and Recreation is renovating the play area at Lakewood Playground. Community input is essential for a successful renovation. Please participate in this quick survey and join us at the upcoming meetings listed below:

These are community meetings; all are encouraged to attend. Bring the whole family!  

Meeting #1 - Open House
Wednesday, October 16, 2019, 6:30 - 7:30 P.M.
Hawthorne Elementary School, Cafeteria, 4100 39th Ave S 

Meeting #2 - Review Design Options and Preferred Design
Tuesday,  December 10, 2019, 6:30 - 7:30 P.M.
Hawthorne Elementary School, Cafeteria, 4100 39th Ave S  

View or download the event poster in these langauges:

This project will update the play area with new play equipment that meets current safety standards. The new equipment will improve access to the play area in conformance with the American with Disabilities Act (ADA) standards.

Location

Lakewood Playground5013 S Angeline Street, 98118

Budget

The Seattle Parks District provides $320,000 in major maintenance funding for this project.  

Schedule

Planning: Winter 2019/20
Design: Winter - Spring 2020
Construction: Late Summer 2020 - Winter 2020/21

Project Description

This project will update the play area with new play equipment that meets current safety standards. The new equipment will improve access to the play area in conformance with the American with Disabilities Act (ADA) standards.

During construction the contractor will need to close the play area and possibly the playfield if required. Seattle Parks and Recreation and the contractor hired for the project will work to minimize impact to the park. 

Community Participation

Please watch this page for opportunities to participate in the public process, which is expected to begin in 2019.