High Point Play Area Renovation

Updated: June 1, 2017

Spring/Summer 2017

Planning is beginning for renovation of the play area. Thank you to everyone who visited the Open House and gave your input on the play area renovation and to everyone who attended the April 8 and May 3 public meetings. Please see notes below.

Due to permitting delays, the project has been slightly delayed. We anticipate starting construction in the spring of 2018 with completion by summer 2018.

Play area will be closed during construction.

Location

High Point Community Center Play Area, 6920 34th Ave SW, 98126

Budget

The Seattle Park District provides $700,000 for planning, design and construction. This Seattle Park District project will replace playground equipment which will include play elements and access for children of all ages and abilities. 

Schedule

Planning: January - March 2017
Design: March - May 2017
Construction:  Spring 2018
Completion: Summer 2018

Project Description

This Seattle Park District project will replace playground equipment which will include play elements and access for children of all ages and abilities.

Community Participation

High Point Play Area Renovation Survey Results

Public Meetings Poster in Six Languages (Amharic; English; Oromo; Somali; Spanish; Tigrigna)

Public Meeting and Open House 2/25/2017

Public Meetings 4/8 and 5/3/2017