Discovery Park Play Area Renovation

Updated: December 7, 2017

Winter 2017/18

Play area is open. Fencing will remain around hydroseeded area while turf establishes.
Download renderings of the new play equipment

Thank you for your cooperation and patience during construction. We look forward to seeing you at the ribbon cutting on Thursday December 28.

Thank you to everyone who participated in the public meeting at the Discovery Park Environmental Learning Center in April 2016. Information from the meeting is located below.

Location

Discovery Park, 3801 Discovery Park Blvd, 98199

Budget

The Seattle Park District provides $550,000 in funding for planning, design and construction.

Schedule

Planning: Fall 2015 - Spring 2016
Design: Spring 2016 - Spring 2017
Construction: Summer 2017 - Fall 2017
Completion: Fall/Winter 2017

Project Description

Replace playground equipment which will include play elements and access for children of all ages and abilities.

Community Participation

Public Meeting 4/23/2016