Fall at Skagit Hydroelectric Project, Photo by Kevin Lidtka
Seattle City Light LARRY WEIS, General Manager and CEO
Denny Substation Project
MY ACCOUNT
Pay My Bill   
generation to transmission to distribution graphic

Future Transmission

As part of the Environmental Impact Statement (EIS), City Light evaluated three alternative routes for a new transmission line to connect the proposed Denny Substation to the existing Massachusetts Substation located in the SODO area.

Once constructed, the transmission line will operate at 115 kilovolts (kV) with the capability to operate at 230 kV in the future as electrical demand increases and more areas of North Downtown Seattle are switched to a network distribution system.

The three transmission alternatives considered through the SEPA EIS process were:
  • Alternative TL1 - A route primarily along the eastern edge of the downtown commercial core
  • Alternative TL2 - A route through the Downtown Seattle Transit Tunnel (sometimes referred to as the bus tunnel)
  • Alternative TL3 - A route along the east side of Interstate-5 (I-5)

Each of the three alternatives, as currently conceived, transition from underground to overhead structures at the southern end before entering the Massachusetts Substation.

After additional engineering work City Light determined that the route through the Downtown Transit Tunnel was no longer feasible. A hybrid alternative – one that travels north on 6th Avenue, crosses under I-5 at James Street and connects to the substation primarily via 7th and Boren avenues – replaces the Transit Tunnel alternative. The Denny Substation Program map shows the three alternatives currently being considered. City Light will identify a preferred alternative in early 2017 after additional engineering work is conducted.

Design of the transmission line will begin once the preferred alternative is selected. The design process is anticipated to take place from mid-2017 through the end of 2018. Construction of the transmission line is anticipated to start in 2019 and to be complete in late 2020. An existing transmission line (the Pine-Broad Substation transmission line) will be used to power the new Denny Substation prior to completion of the new transmission line in 2020.


click image for larger view
Twitter Newsfeed
contact us

Get email updates:

If you have a comment or question regarding this project, please use the box below:

Email:


First
Name:
Last
Name:

Comment/Question:

Subscribe me


If your email requires a response, you will receive follow-up within 48 hours.

Project Hotline:
(206) 257-2142

Email Address:
SCL_DennySub@seattle.gov

Utility Discounts
SAVE 60%
The Utility Discount Program is a great way to lower bills.

LEARN MORE  


  • Contact Seattle City Light

    700 5th Avenue
    Suite 3200
    P.O. Box 34023
    Seattle, WA 98124-4023


    Account & General Questions:


    Contact Us