10000 West Marginal Place South

Posting Date: 3/6/2001                

Contact: Joe Abad - Coordinator

Phone: (206) 684-3012
Rebuild overhead electric power line between Duwamish Substation (10000 West Marginal Place South)and East Marginal Way South and South 124th Street. Line route is as follows: from the southwest side of the substation, passes over Frontage Road and State Route 599 to the southwest side of the high voltage power line corridor. There it turns southeast and follows the corridor to the west side of East Marignal Way where it turns south to South 124th Street.

Construction Start: About May 2001-

Duration: Original 3 to 4 months, additional work added

Daily Work Schedule: As of December 12, 2002

Alternate Contact: -

Alternative Contact Phone:

Related Content

Streetlight Repair
Seattle City Light operates about 84,000 street lights throughout our service territory to help drivers and pedestrians stay safe at night.

Joint Use Engineering
Information on Joint Use, double poles & utility pole odors.

contact us

Contact Customer Service
Or submit an inquiry online

Utility Discounts
SAVE 60%
The Utility Discount Program is a great way to lower bills.


  • Contact Seattle City Light

    700 5th Avenue
    Suite 3200
    P.O. Box 34023
    Seattle, WA 98124-4023

    Account & General Questions:

    Contact Us