6th Avenue South between South Horton and Royal Br

Posting Date: 2/7/2001                

Contact: Bill Challender - Project coordinator

Phone: (206)615-1408
Seattle City Light crews will rebuild the overhead power line to provide increased capacity. The route is from: 4th Avenue South & South Bradford Street to the east side of 4th Avenue South, northbound to the south side of South Horton Street, eastbound to the west side of 6th Avenue South, then northbound to Royal Brougham Way South.

Construction Start: Approximately Mid March

Duration: four to five months

Daily Work Schedule: As of February 7, 2001

Alternate Contact: Marilyn Mar - Construction Project Communications

Alternative Contact Phone: (206) 684-3794

Related Content

Streetlight Repair
Seattle City Light operates about 84,000 street lights throughout our service territory to help drivers and pedestrians stay safe at night.

Joint Use Engineering
Information on Joint Use, double poles & utility pole odors.

contact us

Contact Customer Service
Or submit an inquiry online

Utility Discounts
SAVE 60%
The Utility Discount Program is a great way to lower bills.


  • Contact Seattle City Light

    700 5th Avenue
    Suite 3200
    P.O. Box 34023
    Seattle, WA 98124-4023

    Account & General Questions:

    Contact Us