Fall at Skagit Hydroelectric Project, Photo by Kevin Lidtka
Seattle City Light JIM BAGGS, Interim General Manager and CEO
At Work in Your Neighborhood
MY ACCOUNT
Pay My Bill   

Project Details

South Washington Street Infrastructure Improvement


Posting Date: 7/14/2017                

Contact: Michael Danielsen - Project Manager

Phone: 206-684-3907

PROJECT UPDATE 10/27/17

Crews currently working on the west side of the intersection, where they expect that the shoring and trenching will take extra time due to the depth required.

PROJECT OVERVIEW

Seattle City Light plans to maintain the electrical reliability in the Pioneer Square area. Crews must excavate to connect and repair underground conduits (duct banks) and then pull in new electrical cable at vaults along South Washington Street. The work will start near the alley west of First Avenue South and continue through its intersection with Alaskan Way South. The plan is to complete the work in two stages.

CONSTRUCTION WORK STAGES AND IMPACT DETAILS

Stage 1 Impact Details: 

  • Work zone is on the north side of South Washington Street from the alley between 1st Avenue South and Alaskan Way South.
  • Traffic: There will be local access only onto South Washington Street and only from 1st Avenue South.
  • Parking will be closed on both sides of the street from 9 a.m. to 3 p.m. week days and 9 a.m. to 6 p.m. weekends (intermittent). Two or more spaces will be taken overnight on the north side of South Washington Street to stage equipment. South side parking on South Washington Street will reopen at night.

Stage 2 Impact Details:

  • Work zone: Only one half of the intersection will be worked on at a time.
  • Traffic will be reduced to one lane in both directions on Alaskan Way South and west bound only on South Washington Street.
  • Parking will be closed from 9 a.m. to 3 p.m. week days and 9 a.m. to 6 p.m. weekends (intermittent). Two or more spaces will be taken overnight on South Washington Street to stage equipment.
  • Bicycle trails will be closed when crews are working on the east side of the intersection. At that time bicyclists will need to merge with traffic in work zone. Uniformed police officers will be on site during both stages and at all times to assist with local traffic and pedestrian access.

PROJECT BENEFITS

  • Improve the electrical infrastructure and reliability in the area.

GENERAL PROJECT IMPACTS AND MITIGATION

  • No power outages are expected. Heavy equipment and trucks will be located at the worksite.
  • Traffic, parking, and pedestrian impacts will occur near the worksite to promote safety and accommodate equipment.
  • Excavation will be covered with steel plates during non-work hours.
  • Weekend work will take place intermittently. No work will occur two hours before and for two hours after major Pioneer Square/South of Downtown (SoDo) events.
  • Crews will pull the electrical cable into the duct banks at a later date. That work involves crews working at vaults only, so it has a much smaller impact.

SCHEDULE

Construction Start: As early as August 1, 2017

Duration: August to Fall of 2017

Daily Work Schedule: Mon-Fri, 9am-3pm; intermittent weekends 9am-6pm
ALTERNATE CONTACT INFORMATION

Alternate Contact: -

Alternative Contact Phone:

Related Content

Streetlight Repair
Seattle City Light operates about 84,000 street lights throughout our service territory to help drivers and pedestrians stay safe at night.

Joint Use Engineering
Information on Joint Use, double poles & utility pole odors.

contact us

Contact Customer Service
206.684.3000
Or submit an inquiry online

Utility Discounts
SAVE 60%
The Utility Discount Program is a great way to lower bills.

LEARN MORE  


  • Contact Seattle City Light

    700 5th Avenue
    Suite 3200
    P.O. Box 34023
    Seattle, WA 98124-4023


    Account & General Questions:


    Contact Us