Fall at Skagit Hydroelectric Project, Photo by Kevin Lidtka
Seattle City Light LARRY WEIS, General Manager and CEO
At Work in Your Neighborhood
MY ACCOUNT
Pay My Bill   

Project Details

French Creek Transmission Poles


Posting Date: 6/6/2016                

Contact: Kee Leung - Sr.,Electrical Engineering Specialist

Phone: 206-684-3082

PROJECT UPDATE (8/8/2017)

Crews have erected the four new mono steel poles and removed/salvaged a total of five old lattice towers.  They have transferred new sets of power lines along the new poles. Equipment installation will continue through 9/14/17 and the project should be completed with the construction area restored by approximately 11/30/2017.

PROJECT OVERVIEW

Seattle City Light will construct four electric transmission poles along French Creek west of the intersection of 363rd Avenue NE and SR 530 east of Arlington. The creek is eroding its bank near two steel towers, jeopardizing their stability. The new poles are needed to maintain regional electrical reliability. Seattle City Light will relocate and replace two towers with steel poles, remove one existing steel tower entirely, and construct two additional steel poles for a total of four new poles. See the map for the tower/pole arrangements. Contractors will improve access roads so that equipment can be transported to the site, then build pads and piers for the placement of the new poles. City Light will erect the poles and transfer the power lines over two seasons. This phasing is necessary to maintain electrical service.

Map of the Construction Work Zone


PROJECT BENEFITS

  • The work will upgrade infrastructure and increase the reliability of the transmission system.
  • A total of five steel towers will be replaced by four steel monopoles.

PROJECT IMPACTS

  • The new poles will be 200’ tall, compared to the current towers which range from 90’-115’ tall.
  • Heavy equipment and trucks will be at each temporary construction pad and tower location.
  • Neighbors should expect vehicle traffic and construction noise during work hours.
  • No power outages related to transmission line work are anticipated.

PROJECT DURATION DETAILS

  • Season One: Suspended. See update above
  • Season Two: Approximately fall, 2017.

SCHEDULE

Construction Start: July 11th, 2016

Duration: Two seasons, see text above

Daily Work Schedule: Weekdays and Saturdays from 7 a.m. to 3 p.m.
ALTERNATE CONTACT INFORMATION

Alternate Contact: -

Alternative Contact Phone:

Related Content

Streetlight Repair
Seattle City Light operates about 84,000 street lights throughout our service territory to help drivers and pedestrians stay safe at night.

Joint Use Engineering
Information on Joint Use, double poles & utility pole odors.

contact us

Contact Customer Service
206.684.3000
Or submit an inquiry online

Utility Discounts
SAVE 60%
The Utility Discount Program is a great way to lower bills.

LEARN MORE  


  • Contact Seattle City Light

    700 5th Avenue
    Suite 3200
    P.O. Box 34023
    Seattle, WA 98124-4023


    Account & General Questions:


    Contact Us