Project Details Information
|
Release Date: |
3/20/2001
|
|
Contact: |
Bill Challender - Coordinator
phone: (206)615-1408
|
|
Alternate Contact: |
Marilyn Mar - Construction Project Communications
phone: (206)684-3794
|
| |
|
|
Work planned on: East Marginal Way South, 3rd Avenue South to South
|
|
City Light crews will rebuild overhead electric power lines located on the southwest side of East Marginal Way South between 3rd Avenue South and South Webster Street. The work will include replacing two lines of old wire with new higher capacity wire as well as the removal of an older line. Poles, cross arms and associated equipment will also be replaced.
|
|
Schedule: As of March 20, 2001 |
|
Begin: About mid April |
|
Duration: Three to Four Months |
|
|
|
Customer Service
|
|
Call (206) 684-3000
|
|
|