Project Details Information

Release Date: 6/5/2013
Contact: Roy Carbonell - Electrical Service Representative
phone: 206-386-1692
Alternate Contact: -
phone:
   
Work planned on: Mount Baker: Shoreland Dr. S to S Andover St.

Seattle City Light has been replacing aging electrical cable in the Mt. Baker neighborhood in phases over the last several years. We plan to come to the section bounded by Shoreland Drive S. on the north, S. Andover Street on the south, and between Lakewood Avenue S on the east and Hunter Boulevard S on the west starting the third week of June to continue the upgrades. (See Mount Baker Map)

The cable in the neighborhood is thirty or more years old. It is now reaching the end of its expected useful life. It needs to be replaced to improve the reliability of electrical service and to help avoid unplanned outages. We anticipate being in the project area for approximately six weeks. During that time we will be working at electrical vaults pulling and splicing electrical cable. Accessory equipment like insulative connectors and transformers will also be replaced on an as needed basis.

What You Can Expect

  • Planned Power outages so crews can safely do the work.
  • Customers can expect a minimum of five planned outages.
  • The project's outages are on Tuesday and Thursdays and will last from approximately 8 a.m. to 4 p.m.
  • Notification by letter two weeks in advance specifying the exact date of your outage. Door hangers may be used to communicate as crews discover additional work. These will be placed 48 hours in advance.
  • Work begins the third week of June and will last approximately 6 weeks.
  • There will be some traffic and parking disruptions in the immediate work area, but it will be signed. Work will be done at a vault so there is no trenching planned. Flaggers will be used where needed on residential streets.

9/12/2013 Update: This project has been completed

Schedule: June-July, 2013
Begin: June 20, 2013
Duration: 6 weeks
Click here for more contact information! Customer Service
Call (206) 684-3000
   



 
More City of Seattle Construction Projects:
   
  Send questions or comments to Mark VanOss by email or call Mark at 206.684.3279.
   
  Home | North | South | Downtown ---- Archives

The Seattle City Light Web Team:

Seattle City Light -- 700 5th Avenue, Suite 3200, Seattle, WA 98104-5031 -- 206.684.3000
Mailing address: 700 5th Avenue, Suite 3200, P.O. Box 34023 Seattle, WA 98124-4023