Project Details Information
|
Release Date: |
10/25/2010
|
|
Contact: |
Mark VanOss - Sr., Public Relations Specialist
phone: (206) 684-3279
|
|
Alternate Contact: |
-
phone:
|
| |
|
|
Work planned on: Gatewood Hills in West Seattle
|
|
Original Project Description: Underground power cables will be injected with silicone to fill cracks in their protective insulation. The work will be between Southwest Holly Street on the north, Southwest Frontenac Street on the south, 38th Avenue Southwest on the east and 41st Avenue Southwest on the west. Several planned outages will be required during the project to complete the testing and injection portion of the work, but the outages will not fall on consecutive days. The contractor will notify you on the Thursday evening prior to the next week's outages.
<
|
|
Schedule: planned for late November 2010 for three weeks |
|
Begin: planned for November 29 |
|
Duration: testing and injection portion planned for 3 weeks |
|
|
|