Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
City Light crew

Project Details Information

Release Date: 12/17/2013
Contact: Bob Stewart - Project Manager
phone: (206) 684-7977
Alternate Contact: -
phone:
   
Work planned on: View Ridge Conduit Installation

Project Overview
Underground electric cable in View Ridge was buried directly in the ground from 1969 to 1974 using the technology and materials available at the time. As underground cables age, the protective insulation deteriorates. In 2009 and 2010, Seattle City Light tested and, where possible, injected the cable with silicon. The silicon injection process extends the life of the cable by at least 20 years. Approximately 60 percent of the cable that was tested was injected. The other 40 percent of the cable in the neighborhood was tested but found not suitable for injection. That 40 percent must now be replaced. The next step in replacement is installation of conduit. Seattle City Light is hiring a contractor to install conduit and associated work, including new electrical vaults; curb ramp installation and restoration, sidewalks, pavement, and landscaping. The final step will be pulling the cable into the protective conduit by Seattle City Light crews.

Project Update
In 2012, test holes were drilled to determine the location of other utilities that are near where the conduit will be installed. The conduit will be installed by tunneling beneath the ground's surface. This method is called horizontal-directional drilling (HDD). HDD is much less disruptive to sidewalks and landscaping than open trenching. It is also a less expensive, faster means of replacing the electrical system. City Light's Resident Engineer will be on-site to monitor the contractor.

The status of your electric cable may have changed due to the need to make emergency repairs since the original silicon injection project. A map showing the locations where new conduit and vault installations are necessary and a construction schedule by area can be found here.

11/25/2014 Update
Refer to map above. The following segments have conduit installed:
  • Sand Point Country Club
  • Central Segments
  • Northeastern Segments
  • Southeastern Segments
Additionally, the Sand Point Country Club has had its underground electrical cable replaced. Cable replacement will not start in the finished segments until 2015. Details are still being worked out.

The View Ridge Southern Segment has its own Website.

Schedule: 
Begin: December 19, 2013
Duration: 10 months
Click here for more contact information! Customer Service
Call (206) 684-3000
   



 
More City of Seattle Construction Projects:
   
 
   
  Home | North | South | Downtown ---- Archives