Project Details Information
|
Release Date: |
6/23/2006
|
|
Contact: |
David Van Holde - Account Executive
phone: 206-233-3867
|
|
Alternate Contact: |
Marilyn Mar - Communications & Public Relations
phone: 206-684-3794
|
| |
|
|
Work planned on: Northgate
|
|
Work locations: 1st Avenue Northeast from Northeast 95th Street to Northeast 112th Street; 5th Avenue. Northeast from Northeast 95th Street to Northeast 125th Street. City Light will rebuild portions of the existing overhead distribution system. All work will be planned so that community impacts are minimal. The purpose of this work is to provide more capacity and redundancy to the system, to accommodate new, additional load to the Northgate area.
|
|
Schedule: Variable |
|
Begin: May 2007 |
|
Duration: Up to 10 months starting May 2007 |
|
|
|
Customer Service
|
|