Project Details Information

Release Date: 6/10/2005
Contact: Faz Kasraie - Manager
phone: 206 615 0620
Alternate Contact: Ray Ramos - Supervisor
phone: 206 615 0610
Work planned on: West Side of Elliott Avenue from West Mercer to De
Place new poles and two new circuits of 954 mcm 26 kv power lines from West Mercer to the foot of Denny Way along the West side of Elliott Avenue.
Begin: June 2005
Duration: 4 months