Project Details Information

Release Date: 4/6/2005
Contact: Jeri Emunson - Crew Chief
phone: 206 386 1646
Alternate Contact: Ray Ramos - Supervisor
phone: 206 615 0610
   
Work planned on: 15th Avenue Northeast Alley between 47th and 50th
Install ducts and hand hole in alley. Intercept existing conduit and install new underground service.
Schedule: 
Begin: April 11, 2005
Duration: 4 days