Project Details Information

Release Date: 3/7/2005
Contact: Don Nelson - Senior Management Systems Analyst
phone: (206) 684-3467
Alternate Contact: James Martos - Civil Construction Supervisor
phone: (206) 386-1637
   
Work planned on: 1st Avenue Alley and Cherry Street
In ground electrical facilities and duct bank rebuild. The duct bank crosses Cherry Street between 1st Avenue and 2nd Avenue.
Schedule: 4th quarter 2005
Begin: 3rd quarter 2005
Duration: 3.5 months