Project Details Information

Release Date: 3/3/2005
Contact: Don Nelson - Senior Management System Analyst
phone: (206) 684.3467
Alternate Contact: James Martos - Civil Construction Supervisor
phone: (206) 386-1637
   
Work planned on: 9th Avenue and Jefferson
Construction of a new duct bank and electrical vault to provide electrical service to new building for Harborview IEB.
Schedule: Start first quarter 2006
Begin: Start first quarter 2006
Duration: 9 months