City Light crew

Project Details Information

Release Date: 3/1/2005
Contact: Don Nelson - Senior Management Systems Analyst
phone: (206) 684-3467
Alternate Contact: James Martos - Civil Construction Supervisor
phone: (206) 386-1637
Work planned on: 3rd Avenue Lenora Street and Blanchard Street
Seattle City Light will construct a new vault and ducts on the west side on 3rd Avenue between Lenora Street to Blanchard Street City Light will work with the Seattle Department of Transportation in restoring the driving lane.
Schedule: Continued from 2004
Begin: Last quarter 2004
Duration: 2 months - 20% complete as of 06/24/05