Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
City Light crew

Project Details Information

Release Date: 3/1/2005
Contact: Don Nelson - Senior Management Systems Analyst
phone: (206) 684-3467
Alternate Contact: James Martos - Civil Construction Supervisor
phone: (206) 386-1637
   
Work planned on: 3rd Avenue Lenora Street and Blanchard Street
Seattle City Light will construct a new vault and ducts on the west side on 3rd Avenue between Lenora Street to Blanchard Street City Light will work with the Seattle Department of Transportation in restoring the driving lane.
Schedule: Continued from 2004
Begin: Last quarter 2004
Duration: 2 months - 20% complete as of 06/24/05
Click here for more contact information! Customer Service
Call (206) 684-3000
   



 
More City of Seattle Construction Projects:
   
 
   
  Home | North | South | Downtown ---- Archives