Project Details Information

Release Date: 2/28/2005
Contact: Don Nelson - Senior Management Systems Analyst
phone: (206) 684-3467
Alternate Contact: James Martos - Civil Construction Supervisor
phone: (206) 366-1637
Work planned on: 159 Denny Way
Construction of a new underground electrical service in the alley adjacent to 159 Denny Way.
Schedule: First quarter of 2005
Begin: First quarter of 2005
Duration: 6 weeks