Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
City Light crew

Project Details Information

Release Date: 2/28/2005
Contact: Don Nelson - Senior Management Systems Analyst
phone: (206) 684-3467
Alternate Contact: James Martos - Civil Construction Supervisor
phone: (206) 366-1637
   
Work planned on: 159 Denny Way
Construction of a new underground electrical service in the alley adjacent to 159 Denny Way.
Schedule: First quarter of 2005
Begin: First quarter of 2005
Duration: 6 weeks
Click here for more contact information! Customer Service
Call (206) 684-3000
   



 
More City of Seattle Construction Projects:
   
 
   
  Home | North | South | Downtown ---- Archives