Project Details Information

Release Date: 1/8/2002
Contact: Joe Abad - Sr. Project Manager
phone: (206) 684-3012
Alternate Contact: -
phone:
   
Work planned on: Fauntleroy Way Southwest to Southwest Roxbury to S
Replace poles, transformers and conductors to upgrade from a 4kV distribution system to Seattle City Lights standard 26kV distribution system.
Schedule: As of January 8, 2002
Begin: January 13, 2002
Duration: About 6 months