The City of Seattle, Seattle City Light Department ("SCL"),
requests qualifications from qualified consulting firms for On-Call
Energy Management Consulting Services for SCL’s Energy Management Services
Division.
The scope, cost, and timing of the specific assignment will be defined
in detail in an "Authorization for Professional Service," which
is referenced in the Request for Qualifications (RFQ), for each assignment
issued after a contract has been executed. The range of consulting services
required by the contract may include any of the following services:
- Energy Management Technical Expertise
- Energy Management Field Services
- Energy Management Program Support
Please visit our web site at
www.energysmartservices.com
Minimum Qualifications:
Respondents should be experienced in providing Commercial and Industrial
technical, field, and/or program support functions, and have or be willing
to establish a local office within the Seattle metropolitan area for delivery
of services.
The term of the contract shall extend from the date of execution by the
Superintendent of Seattle City Light, or designee, through December 2006.
The final scope of work and level of effort will be determined through
contract negotiations and implemented by specific task orders. The amount
of compensation will be determined at the time of contract negotiations, and
will be conditioned upon satisfactory performance, continued appropriation
authority, and a determination by SCL to proceed. The contract may be
extended for up to two additional years in one-year increments.
SCL’s current budget allocation for the services listed in the RFQ is
approximately $150,000 for 2004. The City may at its’ option, amend the
contract(s) for additional time, funding, and scope subject to continued
appropriation authority of the Seattle City Council
SCL will work with the prospective consultant to identify a budget and
not-to-exceed amounts for each task before it is assigned.
Copies of the Request for Qualifications and any other additional information
may be obtained from Rick Jacobson, telephone number (206) 684-3864, or
Andrew Gibb, telephone number (206) 684-3466. Qualifications must be delivered
by 4:00pm on Friday, May 19, 2004, to the address below:
The City of Seattle, Seattle City Light Department
Re: On-Call Energy Management Consulting Services
PO Box 34023
700 Fifth Avenue, Suite 3000
Seattle, WA 98124-4023
Attention: Ginny Habib, room 3004
The City’s proposed schedule is as follows:
Activity |
Date |
Request for Qualifications Issued |
4/27/04 |
Pre-Qualification Conference –
Key Tower Rm. 3613, 10:00 AM
|
5/4/04 |
Last day for Clarification |
5/7/04 |
Addendum Issued |
5/12/04 |
Qualifications Due |
5/19/04 |
Select finalists |
5/26/04 |
* Interview finalists |
6/2/04 - 6/3/04 |
* Apparent Consultant selected |
6/9/04 |
* Contract negotiations initiated |
6/9/04 |
* Contract negotiations completed |
6/16/04 |
* Finalize contract |
6/21/04 |
|
* These dates are for planning purposes only and may be altered.