The 2016 Stormwater Code and Manual became effective on January 1, 2016. These rules replaced the 2009 Stormwater Code and Directors' Rules, which were administered jointly by Seattle DCI and Seattle Public Utilities (SPU).

Key Milestones

  • April 2014
    We submitted our Draft Stormwater Code and related Stormwater Manual to Ecology for review
  • Winter 2015
    We completed the State Environmental Policy Act environmental review
  • Spring/Summer 2015
    The legislative process and formal public review period began for the 2016 Stormwater Code Update
  • Fall 2015
    We began our Directors' Rule process and formal public review for the 2016 Stormwater Manual Update
  • January 2016
    The 2016 Stormwater Code and Manual became effective

Project Purpose

To make sure our regulations are equivalent to Ecology's 2014 Stormwater Manual and address the following topics:

  • Improve stormwater management for new development in Seattle, including on-site stormwater management (formerly green stormwater infrastructure)
  • Improve the Construction Site Stormwater Runoff Controls requirements
  • Clarify Pollution Prevention, Good Housekeeping, and Operation and Maintenance
  • Update the Source Control and Water Quality Treatment Practices

Still Need Help?


Project Archive

For the complete history of this project, please contact us at (206) 684-8880.