The
Seattle Department of Design, Construction and Land Use(DCLU) has
received an application from Sound Transit for a technical variance from
the standards for nighttime construction noise along the north segment
of the light rail line. The segment
of
the light rail system covered by the application runs from the
Convention Center station to NE 45th Street east of I-5. This
application proposes specific new construction noise limits for six work
sites along the north segment.
Section
25.08.640 of the Seattle Noise Ordinance provides for technical
variances from noise standards when there is no practical means known or
available for the adequate prevention, abatement or control of the noise
involved. As a condition of granting the variance, DCLU may require
mitigation measures.
|
|
|
|
Three
public meetings have been scheduled to hear oral
comments on this application.
May
8, 7:00 - 9:00 p.m.
Seattle Central Community College
1701 Broadway, Rm. 1110
May
10, 7:00 - 9:00 p.m.
University Lutheran Church
1604 NE 50th Street
May
15, 7:00 - 9:00 p.m.
Seward Elementary School
Cafeteria, 2500 Franklin Avenue East
|
|
|
Written comments may be submitted at any time prior to May 19th.
For
copies of the variance application and further information, contact David
George, 206-684-7843.
Please
mail comments to:
DCLU
710 2nd Ave Ste. 200
98104-1703 Attn. David George
or
e-mail:
david.george@ci.seattle.wa.us
|
|