| Parks | Centers & Pools | Activities | Reservations & Permits | Projects & Planning | A - Z Index |
Rainier Beach Community Center and Pool
|
|||||||||||||
Special AnnouncementAre you interested in partnering with Seattle Parks at the Rainier Beach Community Center and Pool?
Please watch this page for more information. |
Facility ClosureRainier Beach Community Center and Pool is closed. A new community center and pool will be rebuilt at the same location, funded by revenues from General Obligation Bonds and real estate excise taxes and scheduled to open in fall of 2013. » Closure Press Release with Relocation Information For information about Rainier Beach Community Center activities after the closure, please see closure press release above or call 206-684-4075. |
Winter/Spring 2012
Construction is ongoing. Demolition of the old building is 75% complete and will be completed by the end of February. Work will then continue on subgrade preparation, plumbing and new footings. The facility is closed until fall 2013.
Parks awarded the contract to CE&C out of Tacoma, WA. CE&C also had the highest percentage for potential Women and Minority Business Enterprise (WMBE) participation.
The new 46,479 sq.ft. building will house the new community center and indoor pool which includes a spraypark. In addition, the community center will include a gym, fitness room, childcare, kitchen, multipurpose room, teen area, game room, computer room, meeting room, arts/crafts room and party room for pool rentals.
On the exterior there will be parking and a play area adjacent to the childcare.
A final meeting for the Rainier Beach Community Center and Pool was held on June 15, 2010. Seattle artists Roy McMakin and Jeffry Mitchell, who will create artwork for the building, made a presentation and answered community concerns and questions.
| LOCATION |
8825 Rainier Ave S, Seattle WA 98118
|
| BUDGET |
$25 Million for total project budget which
includes planning, design and construction for a new RBCC facility. $5 million is a combination of General Obligation Bonds, REET I and REET II. |
| SCHEDULE |
Planning: Spring 2009 - Fall 2010
Design: Spring 2009 - Winter 2010/11
Construction: Summer 2011 - Fall 2013
Completion: 2013
|
This project was developed by Parks in response to the Seattle School District's decision to construct a new South Shore K - 8 School, since the school shared the building with the existing community center and pool.
The new Community Center and pool facility will provide the public with improved and updated recreational opportunities and will complement the two new schools constructed on the site.
During the design process Parks worked with the community to develop the best plan for the community. Three public meetings were held to gather input from the neighborhood and two final design meetings. Additionally, Parks worked with the design team and arranged for meetings with an array of constituencies in the neighborhood to gather input and answer questions. These included:
Valuable information gathered from these meetings was incorporated into the design. Locating the gym and the multipurpose room next to each other and the kitchen will allow for large community gatherings. The design also incorporated the gym opening onto the north plaza for additional room and enjoyment in the sunny weather.
A Project Advisory Team (PAT) listed below was assembled in the beginning of September 2009.
| Paula Johnson F. Sam Gaytan Justina Guyott David Sauvion Leika Suzumura |
Yvette Moy Jibril Anwar Hassen Vic Roberson Alan Abe James Luster |
PAT Meeting #1 09/08/09
PAT Meeting #2 10/20/09 PAT Meeting #3 12/02/09 PAT Meeting #4 03/24/10Public Meeting #1 06/09/09
Public Meeting #2 09/15/09*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.
Open House
March 6, 2012
7 – 8:30 p.m.
South Shore K- 8 School Rotunda
4800 S Henderson St
Seattle, WA 98118
Toby Ressler
Project Manager
800 Maynard Ave S
Suite 300
Seattle, WA 98134
206-615-1482
toby.ressler@seattle.gov
Artist Rendering Schematic Design Summary Presentation 04/13/10 Design Commission Presentation 05/06/10 Presentation 06/15/10 |
|
|
| Home | Partnerships | Park Board | Volunteer | FAQ | Parkways Blog |
|
|